    Assignment No. 01
    Semester: Fall 2019
    CS615 Software Project Management
    Total Marks: 10

    Due Date: 12th Nov 2019

    Assignment no. 1 covers Lec#1 to Lec#6.

    Objectives of Assignment:

    • You will learn the project and its management along with software process models.

    Uploading instructions:

    • Your assignment must be in .doc format. (Any other formats like scan images, PDF, Zip, rar, bmp, etc. will not be accepted).
    • No assignment will be accepted through email.

    Rules for Marking:

    It should be clear that your assignment will not get any credit if:

    • The assignment is submitted after due date.
    • The submitted assignment does not open or file is corrupted.
    • Your assignment is copied from internet, handouts or from any other student
    (Strict disciplinary action will be taken in this case).

    Assignment

    Question 1:
    There are certain activities and definitions mentioned below. You are required to choose the suitable name of these activities or definition from the given names.
    c2d1a50e-d6f6-4da7-b37e-14ae86f75893-image.png

    Name Activity or Definition
    At the time of initiation of project
    Middle of the project, Bulk of the activity developed, Defined in phased Placed in life cycle
    At the time of near to complete the project, Unique in Nature, Required limited time scale, Have special purpose
    Lahore to Islamabad motorway
    Overhead bridge
    Underpass to link Road A to Road B
    Control Traffic flow in Lahore
    Design to achieve a strategic business objective
    Provision of faster, save, secure and international traffic facility in Pakistan

    NOTE: Submit “.doc” file only. Every student should provide his/her own work, exact copying of the assignment (or some portion of the assignment) from the internet or other students will lead to copy case and zero marks will be awarded. Do not put any query on MDB about this assignment, if you have any query then email at [email protected]

    Deadline:
    Your assignment must be uploaded/submitted on or before 12th Nov 2019.


  • Cyberian's Gold

    Solution:

    Name Activity or Definition
    Lesser amount of the funds required At the time of initiation of project
    Maximum funds required Middle of the project, Bulk of the activity developed, Defined in phased Placed in life cycle
    Lesser amount of the funds required At the time of near to complete the project, Unique in Nature, Required limited time scale, Have special purpose
    Project Lahore to Islamabad motorway
    Project Overhead bridge
    Project Underpass to link Road A to Road B
    Project Control Traffic flow in Lahore
    Program Design to achieve a strategic business objective
    Program Provision of faster, save, secure and international traffic facility in Pakistan

  • Cyberian's Gold

    Solution:

    Name Activity or Definition
    Lesser amount of the funds required At the time of initiation of project
    Maximum funds required Middle of the project, Bulk of the activity developed, Defined in phased Placed in life cycle
    Lesser amount of the funds required At the time of near to complete the project, Unique in Nature, Required limited time scale, Have special purpose
    Project Lahore to Islamabad motorway
    Project Overhead bridge
    Project Underpass to link Road A to Road B
    Project Control Traffic flow in Lahore
    Program Design to achieve a strategic business objective
    Program Provision of faster, save, secure and international traffic facility in Pakistan


    Recent Topics