Assignment No. 3 Semester: Spring 2019
CS614 – Data WarehousingTotal Marks: 20
Due Date:
August 01, 2019Objectives:
After completing this assignment the students will be able to:
• Understand parallelism
• Calculate speed-up time for pipelining
• Calculate Costs associated with nested loop joins while indexing is not usedInstructions
Please read the following instructions carefully before submitting assignment:
It should be clear that your assignment will not get any credit if:o Assignment is submitted after due date.
o Submitted assignment does not open or file is corrupt.
o Assignment is copied (From internet/ to from students).
o Assignment is submitted other than word format (.doc, .docx).Assignment
Question No. 1
Consider a garments factory where a Men’s casual shirts are manufactured. Each Shirt requires 15 minutes for completion. The factory management is now interested in introducing a pipeline where cutting, stitching and finalizing the shirt will be done in parallel.
You are required to calculate the Speed-up that could be achieved after implementing pipeline for manufacturing of 25 shirts in a row.
Question No. 2
Consider two database tables X and Y, we are required to join these tables using Nested-Loop Join, Assume that indexing is not used in mentioned tables.
The table information is given as:
Size of Table X = 600 blocks
Size of Table Y = 900 blocks
Qualifying blocks for Table X = 50
Qualifying blocks for Table Y = 100Calculate the join cost for X&Y and also for Y&X; after calculations mention which Table should be the outer one X or Y.
Deadline:
Your assignment must be uploaded on VULMS on or before August 01, 2019. While August 02, 2019 will be a bonus day for assignment submission. After the bonus day, no assignment would be entertained via email. -
Answer will be same after convert.
-
-
-