ADVANCED PRODUCTION PLANNING & INVENTORY CONTROL (MGMT717)
ASSIGNMENT # 1
Due Date: November 27, 2019 Marks: 10 SCENARIO:
The supply chain manager of a manufacturing company is interested in finding the best method of forecasting for a special set of gears that enhances the speed of the car. He is
confused between “Weighted Moving Average” method and “Exponential Smoothing” method. The demand of the product is given in the following table:
Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Demand | 60 | 55 | 43 | 65 | 52 | 42 | 47 | 59 | 63 | 44 | 55 | 49 | ? |
QUESTIONS:
24 hours extra / grace period after the due date are usually available to overcome uploading difficulties. This extra time should only be used to meet the emergencies and above mentioned due dates should always be treated as final to avoid any inconvenience.
Deadline:
• Make sure to upload the solution file before the due date on VULMS.
• Any submission made via email after the due date will not be accepted.
Formatting Guidelines:
• Use the font style “Times New Roman” or “Arial” and font size “12”.
• It is advised to compose your document in MS-Word format.
• You may also compose your assignment in Open Office format.
• Use black and blue font colors only.
Referencing Guidelines:
• Use APA style for referencing and citation. For guidance search “APA reference style” in Google and read various websites containing information for better understanding or visit http://linguistics.byu.edu/faculty/henrichsenl/apa/APA01.html
Rules for Marking
Please note that your assignment will not be graded or graded as Zero (0), if:
• Any of the given instructions is not followed
• It is copied or plagiarized
• It is submitted after the due date.
• The file you uploaded does not open or is corrupt.
Solution: 1.
a) Weighted Moving Average:
Month | Demand | Forecast | Error | Error |
---|---|---|---|---|
1 | 60 | |||
2 | 55 | |||
3 | 43 | |||
4 | 65 | 50.0 | 15.0 | 15.0 |
5 | 52 | 56.4 | -4.4 | 4.4 |
6 | 42 | 54.1 | -12.1 | 12.1 |
7 | 47 | 49.6 | -2.6 | 2.6 |
8 | 59 | 46.5 | 12.5 | 12.5 |
9 | 63 | 52.0 | 11.0 | 11.0 |
10 | 44 | 58.6 | -14.6 | -14.6 |
11 | 55 | 52.7 | 2.3 | 2.3 |
12 | 49 | 53.3 | -4.3 | 4.3 |
13 | ? | 49.8 | Total | 78.8 |
b) Exponential Smoothing:
𝛼=0.2
Month Demand Forecast Error | Error | |||
---|---|---|---|---|
Month | Demand | Forecast | Error | Error |
1 | 60 | 60.00 | ||
2 | 55 | 60.00 | -5.00 | 5.00 |
3 | 43 | 59.00 | -16.00 | 16.00 |
4 | 65 | 55.0 | 9.20 | 9.20 |
5 | 52 | 55.8 | -5.64 | 5.64 |
6 | 42 | 57.64 | -14.51 | 14.51 |
7 | 47 | 56.51 | -6.61 | 6.61 |
8 | 59 | 53.61 | 6.71 | 6.71 |
9 | 63 | 53.63 | 9.37 | 9.37 |
10 | 44 | 55.50 | -11.50 | 11.50 |
11 | 55 | 53.2 | 1.80 | 1.80 |
12 | 49 | 53.56 | -4.56 | 4.56 |
13 | ? | 52.65 | Total | 90.90 |
Solution: 1.
a) Weighted Moving Average:
Month | Demand | Forecast | Error | Error |
---|---|---|---|---|
1 | 60 | |||
2 | 55 | |||
3 | 43 | |||
4 | 65 | 50.0 | 15.0 | 15.0 |
5 | 52 | 56.4 | -4.4 | 4.4 |
6 | 42 | 54.1 | -12.1 | 12.1 |
7 | 47 | 49.6 | -2.6 | 2.6 |
8 | 59 | 46.5 | 12.5 | 12.5 |
9 | 63 | 52.0 | 11.0 | 11.0 |
10 | 44 | 58.6 | -14.6 | -14.6 |
11 | 55 | 52.7 | 2.3 | 2.3 |
12 | 49 | 53.3 | -4.3 | 4.3 |
13 | ? | 49.8 | Total | 78.8 |
b) Exponential Smoothing:
𝛼=0.2
Month Demand Forecast Error | Error | |||
---|---|---|---|---|
Month | Demand | Forecast | Error | Error |
1 | 60 | 60.00 | ||
2 | 55 | 60.00 | -5.00 | 5.00 |
3 | 43 | 59.00 | -16.00 | 16.00 |
4 | 65 | 55.0 | 9.20 | 9.20 |
5 | 52 | 55.8 | -5.64 | 5.64 |
6 | 42 | 57.64 | -14.51 | 14.51 |
7 | 47 | 56.51 | -6.61 | 6.61 |
8 | 59 | 53.61 | 6.71 | 6.71 |
9 | 63 | 53.63 | 9.37 | 9.37 |
10 | 44 | 55.50 | -11.50 | 11.50 |
11 | 55 | 53.2 | 1.80 | 1.80 |
12 | 49 | 53.56 | -4.56 | 4.56 |
13 | ? | 52.65 | Total | 90.90 |