3. Calculate the total float for each activity.
Correct Solution
Answer:
dad4d704-d6f8-44f4-94f2-1ab155a049bb-image.png
Identify the critical path.Answer:
A+C+E+G = 3+2+5+6 = 16
A+D1+F+G = 3+0+3+6 = 12
B+D+F+G = 5+4+3+6 = 18
A+C+D2+F+G = 3+2+0+3+6 = 14
The longest path is and the duration is 18 days.
So, the critical path is .
Answer:
The project completion time is 18 days.